“Primaries & Secondaries” at Restaurant Site, Gateway Hills

Gateway Hills Restaurant Update

May 1-May 5, 2017

Last week’s progress on the Restaurant Site @ Gateway Hills. See what was done last week at +Gateway Hills Bar & Grill.

May 1, 2017

Microsoft Word - 5-1-17 Update.docx

Backfilling primary utility trenches.

Microsoft Word - 5-1-17 Update.docx

Backfilling primary utility trenches.

Microsoft Word - 5-1-17 Update.docx

Backfilling secondary utility trenches.

Microsoft Word - 5-1-17 Update.docx

Excavation for primary roof drains.

Microsoft Word - 5-1-17 Update.docx

Excavation for primary roof drains.

Microsoft Word - 5-1-17 Update.docx

Excavation for secondary power inside of building.

Microsoft Word - 5-1-17 Update.docx

Grounding wires installed in preparation for transformer pad.

Microsoft Word - 5-1-17 Update.docx

Conduits installed into building from transformer.

Microsoft Word - 5-1-17 Update.docx

New poles are on the right side.

Microsoft Word - 5-1-17 Update.docx

Building forms for retaining wall footings, installation of rebar for footings and peirs.

Microsoft Word - 5-1-17 Update.docx

Setting grade pitch of pipe alongside Hiltz.

May 2, 2017

Microsoft Word - 5-2-17 Update.docx

Backfilling of primary & secondary trenches.

Microsoft Word - 5-2-17 Update.docx

Installing grade stakes for front walkway.

Microsoft Word - 5-2-17 Update.docx

Strip forms from footings. Building forms for retaining wall, installing rebar & foundation ties.

Microsoft Word - 5-2-17 Update.docx

Installing primary roof drain pipe.

Microsoft Word - 5-2-17 Update.docx

Installing primary roof drain pipe.

May 3- May 4, 2017

Microsoft Word - 5-3 to 5-4 Update.docx

Excess fill cleanup. Gravel & fabric installed up to top of footing. Final grade & compact of primary & secondary trenches.

Microsoft Word - 5-3 to 5-4 Update.docx

Strip forms from walls.

Microsoft Word - 5-3 to 5-4 Update.docx

Strip forms from walls.

Microsoft Word - 5-3 to 5-4 Update.docx

Installing conduit & sweeps to pole.

Microsoft Word - 5-3 to 5-4 Update.docx

Installing pull box for secondaries outside of building. Connecting conduits through foundation wall.

Microsoft Word - 5-3 to 5-4 Update.docx

Setting transformer pad.

May 5, 2017

Microsoft Word - 5-5-17 Update.docx

Backfilling of interior trenches.

Microsoft Word - 5-5-17 Update.docx

Backfilling of interior trenches.

 

We are still looking for a restaurant operator for this 7,500 SF restaurant space for lease. If you know someone looking to open in a new location, call us today: 603-598-7500!Want to know more?

Visit:http://www.gateway-hills.com/new-restaurant-site/
Follow our progress blogs here:http://gatewayhills.blogspot.com/

Like us on Facebook: Gateway Hills
Follow us on Twitter: @GatewayHills
Follow us on LinkedIn: The John Flatley Company
Like us on Instagram: Gateway Hills
Follow us on Pinterest: GatewayHills